TR Warszawa’s new headquarters was intended to create a contrast between its dark façade and the white Museum of Modern Art. That concept is now obsolete. The Mayor of Warsaw, Rafał Trzaskowski, today unveiled a new design for the building featuring a light-coloured façade, which will be lighter in appearance and cheaper to construct. The construction schedule indicates that the Teatr Rozmaitości is due to open in 2029.
TR Warszawa without a black façade
For the past 10 years, visualisations of the future theatre have cemented the image of a black structure in the minds of Warsaw’s residents. Together with the white museum, it was intended to form a striking composition of two neighbouring institutions. However, Rafał Trzaskowski has announced a change to the façade’s colour and materials. The new façade will be lighter in weight, have a more delicate appearance and will not have as great an environmental impact as the previous design. The Mayor of Warsaw also highlighted the cost savings in the construction, though he did not specify the amount or provide a detailed specification of the new materials. We will therefore have to wait for the publication of more precise data before assessing the financial and environmental benefits.

Thomas Phifer’s design in a new guise
The theatre’s architecture is being designed by the New York-based practice Thomas Phifer and Partners, in collaboration with APA Wojciechowski Architekci and the engineering team at Buro Happold. The building will have five above-ground storeys, a reinforced concrete structure and a steel roof. The total floor area will be 17,146 square metres, of which 11,526 square metres will be above ground. The project is being funded by the City of Warsaw, with the ECM Group Polska and Portico Project Management consortium acting as the contract engineer. The first joint visualisations of the theatre and museum were presented in September 2015. The departure from TR’s black scheme completely alters this concept.
Between the museum and the Palace of Culture
TR Warszawa’s new headquarters is being built on Plac Defilad, between the Museum of Modern Art and the Palace of Culture and Science. Together with the museum, it will form the northern frontage of Plac Centralny. Pedestrian walkways will be retained between the two institutions and between the theatre and the Palace of Culture and Science. In the urban interpretation of the project, this scale is particularly significant, as the lower buildings define the square’s clear boundaries and divide its vast space into smaller sections. The light-coloured façade will soften the existing contrast between the theatre and the museum. However, the significance of the entire complex will depend primarily on the quality of the ground floors, the accessibility of the walkways, and whether local residents are willing to spend time here outside performance hours as well.

How much does the new TR Warszawa headquarters cost?
Funding has influenced the pace of the project from the outset. In 2021, the city’s budget for the project was increased to 288 million zlotys. Meanwhile, in the 2023 tender, the cheapest bid, submitted by Doraco, amounted to approximately 643 million zlotys gross. The tender was cancelled, and the construction was divided into phases. In the subsequent tender, Warbud proposed approximately 52.62 million PLN for the first phase and 33.15 million PLN for the second, totalling approximately 85.78 million PLN. These figures relate to the underground works and the above-ground structure, not the complete, fully equipped theatre. The final cost of the entire project will only be known once the contracts for further works have been awarded.
Two stages and TR Warszawa opening onto the square
The theatre’s main stage will seat up to 700 spectators, whilst the smaller stage, on the first floor, will seat around 150. The flexible layout of the main auditorium will allow the seating to be adapted to different productions. The building will also house rehearsal rooms, audio and video studios, and educational spaces. The foyer, which will be open to the public, will feature a restaurant, a shop, ticket offices and a cloakroom. The basement, in turn, will house storage areas, workshops and access to the museum’s unloading bays. The design also allows for the theatre hall to open out onto the adjacent square. It is precisely this ability to bring events outdoors that gives this architecture its special potential. In a place that for decades has been overshadowed by the immense scale of the Palace of Culture, a space for everyday gatherings may emerge, where culture is also accessible to the casual passer-by.
Source:materials from TR Warszawa,Warsaw City Hall